• @0x4E4F@sh.itjust.worksOP
      link
      fedilink
      English
      17
      edit-2
      3 months ago

      Actually, everything should be done by crane, but I guess management told them to use the forklifts cuz getting and assembling one on site costs a lot.

        • @0x4E4F@sh.itjust.worksOP
          link
          fedilink
          English
          63 months ago

          No, but tell that to Bob from management, who is not an engineer.

          I’ve been in situations like that. You just don’t do it. Also, explain why in written form and have that stamped and submitted.

        • Githyanki
          link
          English
          13 months ago

          I’m going to say less. They can do it by hand now!